HOW IT WORKS — WHOSE CLOCK EACH STEP RUNS ON
THE REAL CAD MODEL — DRAG TO SPIN
01–06 — THE PATH, IN STILLS

01 — PRICE IT YOURSELF
The build tool prices your exact frame in 60 seconds. Start there.

02 — SAME-DAY CALLBACK
A Greenhouse Expert calls about your exact build and starts with your county's design wind speed. That number decides your Series.
03 — PAPER BEFORE DEPOSIT
Before a deposit you hold the itemized quote, the PE-stamped set, and the 10-year metal warranty in writing. The packet is built to forward to a lender.

04 — SEVEN DAYS. A TRUCK.
7 days from deposit to the truck. Pre-assembly runs on our own factory floor, which is how the number holds. One truck carries the whole kit, 364 pieces plus 326 bagged brackets.

05 — YOUR LINES RUN IN PARALLEL
Your permit and your pad run while we build. Sequence them one after another and the same project gives up a month. The full timeline.

06 — FOUR PEOPLE. ONE DRILL.
Your crew of 4 raises it in 10–14 days with an impact drill and one kind of bolt. Want it hired out? A crew gets scoped in your quote.
07 — EVERY LINE, WHOSE CLOCK
LINE
TYPICAL DURATION
WHOSE CLOCK
COUNTY WIND CHECK
Same day, before you sign
Ours
PRODUCTION
7 days to the truck
Ours
PERMIT APPLICATION
Days to weeks, county-dependent
Yours, stamped plans in hand
CONCRETE PAD
1–2 weeks including cure
Your local contractor
ASSEMBLY
10–14 days, 4-person crew
Yours, or a crew scoped in your quote
UTILITIES + CLIMATE EQUIPMENT
Varies with crop and power service
Your trades
The honest schedule-killers, line by line, live in the timeline article.
08 — GROWING
Pad and permit run alongside production, so six to eight weeks after deposit you're walking rows under 14-foot sidewalls.
BEFORE ANY MONEY MOVES
09 — ASKED AND ANSWERED
7 days to the truck, 10–14 days of assembly. With pad and permit run in parallel, most projects are growing inside six to eight weeks of deposit.
4 capable people with an impact drill raise it in 10–14 days, and no crane comes to the site. Prefer turnkey? A crew gets scoped in your quote.
Your county's published design wind speed. It decides your Series, and the permit desk compares it against the stamped plans. We check it before any money moves.
The concrete pad. Book your concrete contractor the day you put down a deposit, and start the permit the same day.
Work backward: two weeks of assembly, two to six weeks of pad and permit in parallel, plus fit-out. For most buyers that's a late-fall deposit.
PRICE IT TODAY — THE TRUCK LOADS IN 7 DAYS